EPUFLOOREPUISORAIL

Innovative prefabricated turnouts at the Poznań depot. A key stage of the modernization has been completed

1 décembre 20252 min de lecture
Innovative prefabricated turnouts at the Poznań depot. A key stage of the modernization has been completed
In the second half of November, modern EPUSLAB turnout slabs were installed at the tram depot on Forteczna Street in Poznań, a system that will enhance durability, safety, and working comfort at the depot. This is part of a broader infrastructure modernization carried out by MPK Poznań.

From November 25 to 27, an important stage of the modernization project was carried out at the Forteczna Tram Depot, involving the installation of prefabricated turnout slabs. This is another modern solution implemented by MPK Poznań to enhance the reliability of tram infrastructure.

As part of the project, prefabricated turnout slabs were installed, prepared by Epufloor in cooperation with Vossloh Switch Systems Poland Sp. z o.o., which supplied steel components adapted to the slabs. Epufloor delivered individually designed prefabricated slabs featuring an exposed aggregate surface texture not previously used in the Polish tram market. This type of surface increases durability and structural resistance while also providing an aesthetic finish capable of withstanding intensive use.

Epufloor also supervised the coordination of the design phase, with particular attention to the compatibility of the prefabricated elements with the steel components, drainage system, and the electric switch control system supplied and installed by Elektroline. Due to the requirement to ensure a full “quiet zone”, an area of track where no steel reinforcement can be present as it could interfere with switch control signal transmission, the slabs were made exclusively with composite reinforcement. This solution does not interfere with the control system and ensures full compatibility of the infrastructure with switch devices.

Additionally, Epufloor was responsible for coordinating the installation of the prefabricated turnout, including leveling the slabs and applying a leveling grout beneath them using a self-leveling, fast-setting cement mortar. The steel components were fixed within the slab channels using ERS technology, with Epuflex ST polyurethane resin systems, ensuring high durability of the solution.

The completion of this stage of modernization marks another step in upgrading the facilities of MPK Poznań and adapting infrastructure to increasingly high operational standards. The project is part of a long-term plan to improve the quality of public transport in the city, both in terms of rolling stock and infrastructure.

Epufloor extends its thanks to the Investor, MPK Poznań, and the General Contractor, Terlan Sp. z o.o., for their trust and cooperation in delivering this project.

Vous avez un projet ? Parlons-en.

Nos experts vous aideront à choisir la meilleure solution pour votre investissement.

Contactez-nous – nous vous conseillerons et proposerons une solution idéale pour votre projet.

Contactez-nous
Contact